Demolition, Enabling Works & Site Clearance of Fire Station

LOCATION Former Fire Station
Bognor Regis
CONTRACT START DATE 25th March 2024
CONTRACT COMPLETION DATE 14th May 2026

Demolition, Enabling Works & Site Clearance of the Former Fire Station, Bognor Regis

Project Overview

Dorton Demolition & Excavation Limited (DDE) was appointed by Whitbread Plc to deliver the demolition and enabling works package for the redevelopment of the former Bognor Regis Fire Station into a new 116-bedroom Premier Inn hotel.

Located immediately adjacent to the Grade II Listed Bognor Regis Town Hall, the project required the careful demolition of the former Fire Station while preserving and enhancing important heritage features that formed part of the historic setting of the listed building.

View of the former Bognor Regis Fire Station from the Regis Centre car park.

View from Clarence Road.

The works were undertaken within a busy town centre environment, surrounded by public car parks, businesses, highways, and occupied council offices. The project demanded meticulous planning, innovative engineering solutions, extensive stakeholder engagement, and exceptional environmental management to enable redevelopment while protecting both the public and the town’s historic fabric.

Key Challenges

Heritage Protection and Conservation

The most significant challenge was preserving the historic character of the site while facilitating demolition.

The former Fire Station contained decorative stonework, a substantial architectural frieze, and historic masonry earmarked for reuse within the redevelopment. Investigations revealed that the stone frieze was deeply embedded within steelwork and fixed using a combination of metal straps, resin bonding, and hard cementitious infill. Existing age-related cracking further increased the risk of damage during removal.

In parallel, the exposed gable elevation of the Grade II Listed Town Hall required protection and enhancement following demolition of the adjoining structure.

Area located between Bognor Regis Town Hall and the former Fire Station.

The separation line is situated immediately to the left of the arched doorway used by staff to access Bognor Regis Town Hall.

Working collaboratively with the Conservation Officer, Structural Engineer, and Design Team, DDE developed a methodology allowing the careful hand dismantling of the historic features while maintaining structural stability throughout the demolition process.

Despite significant technical constraints, most of the decorative stonework and frieze were successfully recovered for restoration and incorporation into the new development, preserving an important element of Bognor Regis’ architectural heritage.

Consequently, the design team reviewed the specification for the exposed party wall and agreed revised details incorporating new brickwork and stone selected to closely match the colour, texture, size, and appearance of the adjoining Grade II Listed Town Hall.

Recovery of the decorative stonework and frieze.

   

Unexpected Ground Conditions

During demolition and excavation works, the team discovered a previously unidentified historic vehicle inspection pit immediately adjacent to the retained party wall.

Historic vehicle inspection pit.

The discovery created a significant structural risk, with investigations revealing inadequate bearing conditions beneath the retained wall.

Rather than adopting a reactive approach, DDE worked closely with the Structural Engineer to redesign the permanent support solution. The inspection pit was incorporated into a revised foundation arrangement comprising sequential underpinning, permanent steel support posts and new foundation construction.

This collaborative engineering solution not only mitigated the risk but delivered a permanent improvement to the retained structure whilst maintaining programme continuity.

Site Transformation Through Demolition and Enabling Works

The area between Bognor Regis Town Hall and the former Fire Station prior to the commencement of works in 2024.

View of the demolition works in progress in 2024.

Installation of permanent structural supports to the retained party wall.

The area between Bognor Regis Town Hall and the former Fire Station prior to the commencement of works in 2026.

The area between Bognor Regis Town Hall and the former Fire Station on completion in 2026.

Innovation and Technical Excellence

The project required a range of bespoke demolition and engineering solutions.

A permanent structural retention scheme was developed to stabilise the retained wall following demolition. The completed works included:

  • Sequential underpinning of retained structures.
  • Installation of permanent steel lateral support posts.
  • Removal of temporary support systems.
  • Construction of a new brick and stone outer leaf.
  • Installation of cast stone copings and architectural detailing.
  • Integration of new extended roof and drainage arrangements.

Where recovery of original bricks proved impractical due to the exceptionally strong sand-and-cement mortar bond, DDE worked with the design team to develop a conservation-led alternative using bespoke replacement materials that replicated the appearance and character of the historic façade.

The result delivered an authentic heritage outcome while ensuring long-term durability and structural integrity.

Community Engagement and Stakeholder Management

The demolition works were undertaken adjacent to an occupied Town Hall and active Council offices which remained operational throughout the contract.

Maintaining safe access and minimising disruption was critical to project success.

DDE implemented a comprehensive stakeholder engagement strategy that included:

  • Regular communication with building occupiers and local stakeholders.
  • Advance notification of potentially disruptive activities.
  • Maintenance of a stakeholder liaison register.
  • Continuous liaison with Arun District Council and project partners.

A bespoke crash deck was erected above the Town Hall’s rear emergency escape route and stores, ensuring uninterrupted access throughout the demolition programme.

The proactive communication strategy generated positive feedback from stakeholders and enabled the works to proceed without significant complaints or disruption.

Environmental Management and Sustainability

Environmental performance was a key project driver.

DDE implemented a comprehensive Construction Environmental Management Plan which addressed:

  • Dust suppression.
  • Noise and vibration control.
  • Traffic management.
  • Waste minimisation.
  • Air-quality management.

Dust suppression measures included water mist cannons, controlled demolition techniques, damping down of haul routes, and continuous monitoring of site conditions.

A detailed Pre-Demolition Waste Audit informed material recovery strategies and contributed directly to the project’s BREEAM objectives.

The project achieved:

99% Recycling and Recovery Rate

Materials were segregated, processed and diverted from landfill wherever practicable through a structured waste management process.

This significantly exceeded the project’s sustainability targets and demonstrated DDE’s commitment to the circular economy and resource efficiency.

Safety Performance

Safety remained the highest priority throughout the project.

Despite the challenges associated with heritage preservation, structural retention, occupied neighbouring buildings and town-centre working conditions, DDE maintained exemplary safety standards.

Key achievements included:

  • Zero reportable accidents.
  • Zero enforcement notices.
  • No non-conformances identified during client health, safety and environmental audits.
  • Full compliance with Whitbread Contractor Standards.
  • Safe operation adjacent to occupied public buildings throughout the works.

The project demonstrated how complex demolition activities can be delivered safely without compromising programme, quality or environmental objectives.

Achievements and Recognition

The project achieved several notable successes:

  • Considerate Constructors Scheme (CCS) registered project.
  • Achieved an Excellent CCS performance rating.
  • Zero reportable accidents.
  • 99% recycling and recovery of demolition waste.
  • Successful preservation of significant heritage features.
  • Delivery adjacent to an occupied Grade II Listed Building without interruption to operations.
  • Positive feedback from CCS auditors regarding environmental management, workforce welfare, stakeholder engagement and community consideration.
  • Full compliance with planning, environmental and heritage requirements.

Outcome

The former Fire Station demolition and enabling works transformed a constrained brownfield site into a development-ready platform for a major town-centre regeneration project.

Through innovative engineering, exemplary stakeholder management, outstanding environmental performance and a commitment to heritage conservation, DDE successfully overcame complex structural and conservation challenges while maintaining the highest standards of safety and quality.

The project enabled the delivery of Whitbread’s new Premier Inn Bognor Regis Town Centre, which officially opened in May 2026, creating new employment opportunities, supporting local tourism, and contributing to the ongoing regeneration of Bognor Regis.

Premier Inn Bognor Regis (Seafront) hotel.

The scheme stands as an excellent example of how demolition can act as the catalyst for regeneration while preserving the historic character and significance of the built environment.

Replication of the original fire station’s feature panels and signage on the new Premier Inn Bognor Regis.

Project Dates

  • Date of possession: 25th March 2024
  • Completion date (Demolition & Enabling Works): 21st June 2024
  • Return to site: 30th March 2026
  • Completion date (Party Wall Works): 14th May 2026